Passed Density Testing today at 12:30 P.M. Poured footings today at 1:30 P.M. Will Start Rockwall Construction Friday 10-18-2013.
|
| Tamper the Footings |
| Rebar West Footing |
| Rebar North Footings |
| Pouring West Footings |
| Pouring North Footings |
Passed Density Testing today at 12:30 P.M. Poured footings today at 1:30 P.M. Will Start Rockwall Construction Friday 10-18-2013.
|
| Tamper the Footings |
| Rebar West Footing |
| Rebar North Footings |
| Pouring West Footings |
| Pouring North Footings |
| Finally all three permits!!! |
| Starting to move dirt. |
| Sink hole at Stanton and Festival. No water in the Sanctuary for the past 12 hours. El Paso Water Utilities plans on another 4 hours without water. |
| Getting ready to start cutting the rear wall. |
| Rear wall cut. |
| Rear wall cut! |
| Moving dirt to start rockwalls
Spoke to Denise at Vision consultants this morning at 7:00 am. Was told that permit will be issued today. Finally!!!!
|